Entries by modrekiwi

Production line installation in Indonesia

The production line was installed as part of the modernisation of an existing system with a capacity of 3 tonnes per hour. We completed the entire installation with local employees, who we trained for the installation, as well as ensuring the implementation of the quality and security of the construction site according to European standards. […]

Auditing of a waste-incineration plant in Netherlands

Auditing of a waste-incineration plant in Netherlands. The waste flow rate is 26.5 t/h. The furnace chamber contains 3 lanes. 9 elements, including the roof units are water-cooled and a further 6 elements are air-cooled. We assigned a team of 50 employees for this project. This included mechanics, fitters, foremen, construction site management, engineers, locksmiths […]

Auditing assistance in Switzerland

Auditing assistance, automotive industry. Production line for the manufacture of welded precision steel tubes. In the final product, these tubes can be used for piston rod cylinder barrels. These tubes are bent into a round shape from flat bars, welded, the weld joint is sliced and finally the tubes are pulled through a cavity so […]

Installation of a production line in Turkey

Installation of a new production line with a capacity of 5 tonnes per hour. The entire installation was completed with local employees, who we trained for the installation, as well as ensuring the implementation of the quality and security of the construction site according to European standards. The following plant components were incorporated into the […]

Installation of a production line in Venezuela

Installation of a new production line with a capacity of 4.55 tonnes per hour. The entire installation was completed with local employees, who we trained for the installation, as well as ensuring the implementation of the quality and security of the construction site according to European standards. The following plant components were incorporated into the […]